California Enacts SB 440 and SB 61: Major Changes to Private Construction Contracting (Effective 2026)

California legislature has created two new laws that will affect all private construction contracts entered into after January 1, 2026. SB 440 creates a statutorily required change order management dispute process. SB 61 caps retention at 5% for both Owners and General Contractors on private construction projects. These laws are set forth below:

California SB 440 (Civ. Code §§ 8850-8851)
Private Works Change Order Fair Payment Act

Effective Date: January 1, 2026

  • Applies to contractors and subcontractors performing work on private construction projects in California pursuant to contracts entered into on or after January 1, 2026. The law remains in effect until January 1, 2030, unless extended.

Purpose: To establish a clear process for resolving change-order and time-extension claims on private works of improvement.

  • SB 440 does not replace existing prompt-payment or dispute-resolution laws under the Civil and Business & Professions Codes. Instead, it adds a clear framework for handling change-order claims that can be slow and costly to resolve by adding a new Civil Code section 8850 entitled “Claims and Disputes.”

Claim Process: Contractors must submit a detailed, documented claim within 60 days of discovering the issue.

  • 30-Day Owner Response: Owners must meet and confer within 30 days, then identify which portions are disputed or undisputed.
  • 10-Day Follow-Up: After that meeting, owners have 10 days to issue a written confirmation—failure to do so is treated as disputing the claim.
  • 60-Day Payment Window: Undisputed portions must be paid within 60 days, or interest accrues at 2% per month (24% annual).
  • Mandatory Mediation: Disputed items proceed to non-binding mediation before any litigation or arbitration. Contract language attempting to waive or delay this right is void as against public policy.
  • Stop-Work Authority: If owners ignore timelines or refuse mediation, contractors have a nonwaivable right to issue a stop-work notice and suspend work 40 days later.
  • Freedom to Add Reasonable Procedures: Parties may include additional dispute-resolution steps—so long as they don’t delay or dilute SB 440’s protections.

Contractors Should Consider:

  • Review internal change order procedures to conform with SB 440’s timelines.
  • Document change order work thoroughly and contemporaneously.
  • Calendar statutory deadlines immediately upon claim submission.
  • Coordinate with counsel before initiating stop-work rights.
  • Review contract templates to maintain compliance with the statute.

California SB 61 (Civ. Code § 8811)
Limiting Retention on Private Projects

Effective: January 1, 2026.

Purpose: SB 61 caps retention withholdings at 5% for private construction projects. This cap is designed to protect contractors and subcontractors by improving cash flow during the project.

Retention Cap: No more than 5% of any progress payment may be withheld by owners, contractors, or subcontractors.

Aggregate Limit: Total retention cannot exceed 5% of the contract price.

Effective Date: The law is prospective and only applies to contracts executed on or after January 1, 2026.

Exceptions:

  • Residential projects are excluded unless they are mixed-use (both business and residential) or exceed four stories.
  • Subcontractors who fail to provide required performance and payment bonds are not protected by the cap so long as notice of the bonding requirement was given to the contractor in writing before or at the time of bidding.

Attorney’s Fees: Courts must award reasonable attorney’s fees to the prevailing party in disputes over compliance.