The Construction Industry Institute (CII) predicts “there will be an annual growth rate of 9.6% in the offsite construction market” with an estimated worldwide market of $141.4 billion by 2027.1 Modular construction, also called offsite construction, refers to the process in which a building is constructed off-site under controlled plant conditions, using the same materials and designing to the same codes and standards as conventionally built facilities. Effective modular construction projects can finish faster and cost less than traditional onsite construction because fewer labor hours are needed to complete a comparable project, and waste is significantly reduced.2 If your company is involved in modular construction or considering a foray into the offsite construction arena, it’s important to evaluate how allocation of risk is different in the offsite construction industry.
The first issue is always the contract and the law that governs the work. The modular construction contract will differ from the usual contracts used in commercial construction. Because the modules are built off-site, they are considered “goods” that will be governed by the Uniform Commercial Code (“UCC”) unless the contract specifies that common law applies. Application of the UCC changes several aspects of a project that are usually taken for granted, including but not limited to statute of limitations, bond claims, and the common law’s substantial compliance standard versus the UCC’s perfect tender rule. The UCC perfect tender rule requires complete performance and is a much stricter standard. If the UCC standard is applicable, it can substantially delay final payments and impact the contractor’s other rights and obligations. There are several AIA volumetric modular construction contract documents tailored to these types of issues. Consensus Docs also has contracts focusing on agreements between the prefabricator and owner or general contractor.
A second legal consideration is how state lien statutes will be applied to a modular construction project. Because liens are state-specific, their application to modular construction may vary greatly from jurisdiction to jurisdiction. Liens for off-site work or materials have been allowed in cases that do not involve modular construction, but the same principles can apply to modular construction, allowing the modular constructor or its suppliers to lien the property where the modular units are installed rather than where they are fabricated or stored. Whether common law or the UCC will be applicable may also depend on the jurisdiction. Because modular construction may combine both goods and services, some jurisdictions may allow suppliers to claim a mechanic’s lien “for materials furnished on or about the building.” For example, a supplier of the materials may enforce a mechanic’s lien where the supplier furnishes materials to a modular home builder, who incorporates the materials into a structure off-site, then moves the structure and installs it on a piece of real property. See 5500 Coastal Highway Ltd. Partnership v. Electrical Equipment Co., Inc., 305 Md. 532, 505 A.2d 533 (1986) (applying Maryland law where units built in Delaware and installed in Maryland finding a modular unit is not a “building,” in and of itself, but is “materials furnished” for a building under a mechanic’s lien statute).
Delivery of the modules is another issue worth careful analysis. Not only will delivery require detailed coordination, consideration also needs to be given as to which party has the risk for damage of the modules at every point of transport. Delays can be unavoidable and modules can end up stuck in a port or storage lot exposed to the weather and potential damage. Knowing who bears the risk for the modules if damaged in transit, in storage, and before fully installed is key to mitigating damages, should they occur. Insurance coverage needs to be closely evaluated among the parties to ensure complete coverage is in place at each point of fabrication, storage, delivery, and installation. See Polcom USA, LLC v. Affiliated FM Ins. Co., No. 20 CIV. 9206 (NRB), 2023 WL 5573871, at *2 (S.D.N.Y. Aug. 29, 2023) (denying coverage to subcontractor manufacturer where manufacturer’s coverage limited to “site activities only” and damage occurred while stored at port during strike).
Establishing expectations upfront is crucial in modular construction because of the offsite execution, which requires extensive coordination among designers, fabricators, installers, owners, and general contractors. With so many moving parts taking place at different physical locations, covering the allocation of risk requires thoughtful, detailed review and a contract that clearly identifies each party’s responsibilities to ensure the project attains the efficiencies that modular construction can provide.